Omsk Arena: February results
The readiness of the building is more than 63%.
The installation of the facade metal structures and internal partitions is being completed, finishing works are in progress. The installation of the central facade stained-glass window and window units has been started.
The installation of external and internal engineering networks is in progress. Preparatory works for the installation of engineering systems in the bowl are being completed.
More than 1200 people are currently working at the site.