Technical readiness of Arena Omsk exceeds 50%

The Arena Omsk technical readiness is more than 50%.

In 2021, the construction of main structures of the Arena has been carried out. All 6 floors of the building have been built, stands and roofing have been installed.

The glazing of inspection pavilions has been completed. An individual heating unit has been commissioned. The building is supplied with heat.

Thermal insulation of the building is in progress, façade cold loop and thermal envelope structures are being erected, external and internal engineering networks are being mounted. Over 50% of internal partitions have been installed, finishing works are in progress.

Refrigerating equipment for ice preparation has been delivered to the site. Delivery of ventilation equipment has been started.

During the New Year holidays, the construction works will only be stopped for one day - January 1, 2022.

«Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря «Арена Омск»: итоги декабря

Photo album: Construction of Arena Omsk: december

10 Photo

Show

Latest news

Real-time big data brings competitive advantage in KHL – Coach legend Bob Hartley: “Wisehockey helps us in our daily work”

Club

Real-time big data brings competitive advantage in KHL – Coach legend Bob Hartley: “Wisehockey helps us in our daily work”

Russian national team roster for 2022 Olympic Games preparation

Russian national team roster for 2022 Olympic Games preparation

Official KHL announcement on Jan 12 epidemiological situation in the League

KHL

Official KHL announcement on Jan 12 epidemiological situation in the League

The game between Avangard and Salavat Yulaev is canceled

Club

The game between Avangard and Salavat Yulaev is canceled

Back to top
data != null && Array.isArray(data)