Arena construction: March results
The glazing of the central stained-glass window, the installation of façade cold loop and thermal envelope structures are in progress.
Ventilation ducts are being installed in the hockey bowl and preparatory works for the ice sheet arrangement are in progress.
Alongside with that, builders are installing external and internal engineering networks of the main and auxiliary buildings. Finishing works are carried out on floors 1-4.
Lighting poles are being installed around the arena.
The supply of equipment, finishing materials, as well as materials for the neighbourhood improvement continues.